Under Frequency Load Shedding: 4 Vital Stages Made Easy

Share:
Power Systems
Under Frequency Load Shedding: 4 Vital Stages Made Easy

When a large generating unit or an import line trips, grid frequency starts falling within milliseconds. Automatic relays then disconnect planned blocks of load in stages, sacrificing a few feeders so that the rest of the grid stays alive.

UFR Stages df/dt Relays Swing Equation IEGC 2023 Islanding

Under frequency load shedding is the last automatic defence that stops a generation shortfall from turning into a blackout. This guide explains the physics, the four Indian UFR stages, df/dt relays, islanding and how to calculate how fast frequency falls.

Hello everyone, today we are going to learn how under frequency load shedding works, why grid frequency falls after a generator trips, how UFR and df/dt relays are set and how Indian utilities plan load relief.
under frequency load shedding

What Is Under Frequency Load Shedding?

Under frequency load shedding, often shortened to UFLS, is an automatic protection scheme that trips selected distribution feeders in planned steps when system frequency falls below set limits after a loss of generation. By reducing demand quickly, it restores the balance between generation and load before turbines, auxiliaries and protective relays start tripping healthy machines.

Frequency in an AC grid is a direct measure of balance. When generation exceeds load, the rotating machines speed up, and when load exceeds generation, they slow down and frequency drops.

Distribution recloser system of the kind used for automatic load shedding on under frequency
Image credit: NOJA Power. Photo courtesy of NOJA Power, shown here for educational reference.

NOJA Power describes distribution reclosers and feeder breakers as a common place for automatic load shedding, since parts of the network can be dropped progressively instead of losing everything. Once generation again matches load, operators restore those feeders one by one.

Advertisement

Why Grid Frequency Falls After a Trip

All synchronous generators on a grid store kinetic energy in their rotors, and this stored energy, called inertia, feeds the deficit in the first seconds after a trip. The bigger the inertia, the slower the fall, which is why system studies express it as the inertia constant H on a common base, as explained in the per unit system.

Governors then raise turbine output, but they need several seconds to respond. If the frequency nadir would go below what turbines and generator excitation systems can tolerate, load must be removed first.

50 HzIndian nominal frequency
49.90 to 50.05 HzIEGC operating band
4Default UFR stages in India
25 %Total relief of peak demand

The SEL and Xcel Energy paper on faster load shedding notes that hydro units can ride through a frequency drop of about 10 percent, while steam turbines are sensitive to about 5 percent. Low frequency also makes blade resonance a real risk, so turbine makers specify strict time limits for each band.

Do You Know?

Inverter based solar and wind plants have no rotating mass connected to the grid, so they add no natural inertia. NOJA Power notes this is a main reason frequency protection is becoming more common on modern networks.

India's 4 Stage UFR Settings Under IEGC 2023

Minutes of an Eastern Regional Power Committee meeting on automatic load relief, held in July 2024, quote Regulation 29(12) of the CERC Indian Electricity Grid Code 2023. It sets four default under frequency relay stages, effective from 1 October 2023.

StageFrequency SettingShare of ReliefExample Relief, ER FY 2024 25
Stage 149.4 Hz5 % of peak1,383 MW
Stage 249.2 Hz6 % of peak1,660 MW
Stage 349.0 Hz7 % of peak1,937 MW
Stage 448.8 Hz7 % of peak1,937 MW

The same minutes record that total relief is planned at 25 percent of the previous year peak demand, split by a task force as 5, 6, 7 and 7 percent. The Eastern Region proposed a revised total of 6,917 MW, with the frequency set points unchanged.

Each State Load Despatch Centre identifies feeders for every stage and the regional committees audit them. Feeder status usually reaches the control centre through an RTU and SCADA link, so the relief actually available can be checked in real time.

Quick Tip

Never put hospitals, water supply, traction or other essential loads on a UFR feeder list. Choose mixed feeders with steady demand, because a feeder that carries little load at night gives almost no relief when it trips.

Rate of Change of Frequency Formula

For the first moments after a trip, before governors act, the swing equation gives the initial rate of fall. The SEL paper writes it for a 60 Hz system; the same relation for any nominal frequency is shown below.

Initial df/dt = f0 × ΔP ÷ (2 × H)
Time to stage ≈ (f0 minus f stage) ÷ df/dt

ΔP = lost generation as a fraction of total, H = inertia constant in seconds

Example:
f0 = 50 Hz, ΔP = 10 % = 0.10, H = 4 s, stage = 49.4 Hz
df/dt = 50 × 0.10 ÷ (2 × 4) = 5 ÷ 8 = 0.625 Hz/s
Time to 49.4 Hz ≈ 0.6 ÷ 0.625 = 0.96 s

This linear estimate ignores load damping and governor response, so real frequency falls a little slower and the true time is longer. It is still a useful first check on whether relay delay plus breaker time is fast enough.

Frequency Decay Calculator

Initial ROCOF and Time to Reach a UFR Stage
Result
Initial ROCOF 0.625 Hz/s, stage reached in about 0.96 s
Advertisement

Second Worked Example: Sizing State Load Relief

Suppose a state had a peak demand of 20,000 MW last year. The total relief at 25 percent is 5,000 MW, split as 1,000 MW at 49.4 Hz, 1,200 MW at 49.2 Hz and 1,400 MW each at 49.0 Hz and 48.8 Hz.

For under frequency load shedding, feeder loads change with season and hour, so planners use measured feeder demand, not connected load, and add margin. The same diversity ideas used in maximum demand calculation apply when you estimate what a feeder really carries at peak.

The ERPC minutes also note an interim step in which load was shifted from stages 3 and 4 to stages 1 and 2 until new feeders were identified. Early stages that really shed their share reduce the depth of every disturbance.

Fixed Stage, df/dt and Adaptive Schemes

Fixed Frequency Stages

Each relay trips its feeder when frequency stays below a set point for a short delay.

Best for: large interconnected grids
Standard
df/dt Relays

Trip when frequency falls faster than a set rate below an enabling frequency.

Best for: severe losses and low inertia periods
Fast
Adaptive and Wide Area

Use measured disturbance size, PMU data or contingency tables to shed the right amount.

Best for: islanded plants and modern grids
Smart

The task force recommendations recorded in the ERPC minutes describe df/dt stages enabled below 49.9 Hz, with rate settings of 0.10, 0.15 and 0.20 Hz/s. Their load quantum is tied to the largest generating station or peak import in the region, whichever is higher.

Modern numerical relays used for under frequency load shedding combine frequency, df/dt and undervoltage blocking in one device, and many substations send the trips as IEC 61850 GOOSE messages. The SEL paper reports Xcel Energy using a default delay of 6 cycles, with 30 cycles on feeders carrying significant motor load.

Do You Know?

In the South Australia event of September 2016, the SEL paper reports frequency falling at about 6 Hz/s. That is far faster than a typical fixed stage scheme with time delays can follow.

Sequence of Events During a Generation Loss

Unit TripsGeneration suddenly less than demand
Inertia ResponseRotors slow, frequency falls at initial df/dt
Storage and PumpsPumping load trips and storage switches to discharge
UFR Stages ActStages at 49.4, 49.2, 49.0 and 48.8 Hz shed feeders
Governor RecoveryTurbines raise output and frequency settles
RestorationOperators reconnect feeders as reserves allow

The ERPC minutes state that energy storage systems should change from charging to discharging at 49.50 Hz, and that pumping load trips before the first stage. Removing such controllable load first spares ordinary consumers.

Islanding Schemes for Plants and Cities

If frequency keeps falling after all under frequency load shedding stages operate, islanding schemes separate a captive power plant, or a city with its own generation, from the collapsing grid. The island must hold a close match between its own generators and selected load, which needs careful load flow analysis beforehand.

Inside a process plant, a similar internal scheme sheds non essential drives so the captive generators survive a grid outage. Fast breakers matter here, and the choice between types is covered in ACB vs VCB vs SF6 circuit breaker; resynchronising later follows the normal generator synchronizing procedure.

7 Steps to Design an Under Frequency Load Shedding Scheme

1
Collect Grid Data
Gather peak demand, largest unit size and system inertia.
2
Define Stages
Use the code settings, such as the four IEGC stages.
3
Allocate Relief
Split the required MW between stages as directed.
4
Select Feeders
Pick feeders with steady, non essential load.
5
Set Relays
Program pickup, delay and undervoltage block.
6
Simulate Events
Check the nadir for credible and severe trips.
7
Audit Regularly
Verify relay health and feeder load every season.
Myth: Load shedding means the utility is short of power.
Fact: Automatic UFR action is protection after a sudden trip, not planned rationing.
Myth: One big stage is better than four small ones.
Fact: Small staged blocks avoid over shedding and the frequency overshoot that follows.
Myth: df/dt relays replace frequency stages.
Fact: They work alongside fixed stages and need supervision to avoid false trips.
Myth: Once wired, the scheme needs no attention.
Fact: Feeder loads change, so relief must be measured and audited every season.
Advantages of Staged Load Shedding
  • Prevents a full blackout after large trips.
  • Acts within a fraction of a second, without operators.
  • Sheds only as much load as the disturbance needs.
  • Protects turbines from damaging low frequency.
Limitations and Challenges
  • Feeder load varies, so actual relief is uncertain.
  • Fixed stages can be too slow in low inertia periods.
  • Rooftop solar on feeders can reduce net relief.
  • Wrong settings can cause over shedding and overshoot.
Advertisement

Testing and Maintaining UFR Relays

  • Inject a ramp of falling frequency and record pickup and trip time.
  • Verify the undervoltage block and the df/dt enabling frequency.
  • Confirm each relay trips the correct feeder breaker.
  • Check that UFR status and trip events reach SCADA.
  • Measure actual feeder load at peak and off peak hours.
  • Remove essential loads that crept onto shedding feeders.
  • Keep relay clocks synchronised for event analysis.

Correct time stamps let analysts compare relay records from many substations after an under frequency load shedding event, which is why time synchronization with NTP and PTP matters for protection teams too. After the July 2012 grid disturbances in northern and eastern India, regulators pressed strongly for regular checks on UFR and df/dt healthiness.

Quick Tip

When a UFR operates, download the disturbance record before resetting the relay. The frequency trace, the voltage at trip and the exact time tell you whether the setting, the delay and the breaker all performed as intended.

Where Under Frequency Load Shedding Is Applied

National Grids
Statewide feeder groups in every region of India.
Captive Power Plants
Internal shedding to keep the plant running when the grid fails.
Island Grids
Small systems with low inertia need fast df/dt action.
Microgrids
Solar and battery systems shed loads during sudden shortfalls.
DG Backed Facilities
Large sites shed non essential loads on generator overload.

Even on a site supplied by a DG set, a frequency dip on a large motor start can trip sensitive loads, so the generator size must suit the largest step load. Critical control systems should still sit behind a UPS.

ERPC Minutes on Automatic Load Relief

PDF
Minutes of Meeting on AUFLS, Eastern Regional Power Committee
Official minutes covering IEGC 2023 UFR stages, load relief quantum and df/dt settings

Video: How Load Shedding Protects the Grid

Under Frequency Load Shedding FAQ

What is under frequency load shedding?

It is an automatic scheme that trips planned feeder groups when grid frequency falls below set values. It restores the balance between generation and demand after a sudden loss of generation.

Relays act in several stages, so only the needed amount of load is removed. Feeders are restored by operators once enough generation is available again.

What are the UFR stage settings in India?

The Indian Electricity Grid Code 2023 lists four default stages at 49.4, 49.2, 49.0 and 48.8 Hz. These settings took effect from 1 October 2023.

Regional power committees then plan the load relief for each stage separately. Recent planning uses a total of about 25 percent of the previous year peak demand in each region.

Why does frequency fall when a generator trips?

The remaining generators must supply the lost power from the kinetic energy of their rotors. As they slow down, the frequency of the whole synchronous grid falls together.

Governors raise turbine output after a few seconds of delay. Until then, the rate of fall depends mainly on the size of the loss and the system inertia.

What is a df/dt relay?

It measures how fast frequency is changing rather than only its value. It can therefore trip load earlier when a very large loss causes a steep fall.

Indian task force settings discussed by ERPC use rates such as 0.10, 0.15 and 0.20 Hz/s. These elements are enabled only when frequency is already below 49.9 Hz.

How fast must load shedding act?

It must act before frequency reaches limits that trip turbines or auxiliaries. Typical schemes use short relay delays of a few cycles plus breaker time.

Our calculator shows a 10 percent loss with H of 4 seconds reaching 49.4 Hz in about one second. Slow breakers or long delays can therefore let the frequency fall too far.

Which loads should never be on a UFR feeder?

Hospitals, water supply, defence, traction and other essential services should stay off shedding feeders. Their sudden loss can create safety risks far worse than a short planned power cut.

Planners instead choose mixed residential and commercial feeders with fairly steady demand. They also review the list each season as new essential connections appear on the network.

Does rooftop solar affect load shedding?

Yes, because a feeder with heavy solar export may carry little or even reverse power at midday. Tripping it then removes generation as well as load, and the net relief becomes small.

Planners therefore measure net feeder flow at different hours. Some utilities move such feeders to later stages or exclude them from the list.

Advertisement

Related Articles

External References

What We Learn Today

  • Under frequency load shedding trips planned feeder blocks in stages when frequency falls after a generation loss, so the remaining grid avoids a blackout.
  • India uses four default UFR stages at 49.4, 49.2, 49.0 and 48.8 Hz under IEGC 2023, planned at about 25 percent of previous year peak.
  • The initial rate of fall equals f0 times the lost power fraction divided by twice the inertia constant, so low inertia grids need faster df/dt protection.
I hope you like above blog. There is no cost associated in sharing the article in your social media. Thanks for reading!! Happy Learning!!
Author · instrumentationblog.in
Editorial Staff
Instrumentation Blog’s Editorial Staff are industry professionals and technical writers with a strong interest in industrial electrical systems. They specialize in simplifying complex technical concepts into clear, practical, and easy to understand insights. All articles written by the Editorial Staff are technically reviewed before publication.
Technically reviewed on

Leave a Reply

Your email address will not be published. Required fields are marked *