How to Calculate Generator Size for an Industrial Load: 5 Proven Steps to Prevent a Stalled Engine

Share:
Electrical
How to Calculate Generator Size for an Industrial Load: 5 Proven Steps to Prevent a Stalled Engine

A generator sized for the running load alone can pass every check on paper and still fail the moment the biggest motor on site tries to start.

Starting current, not steady-state demand, is what actually stalls an undersized genset.

Running kW vs Starting kVA Live Genset Sizing Calculator Voltage Dip Limits

How to calculate generator size for an industrial load means sizing for the larger of two numbers: total running demand at the site's power factor, or the starting kVA needed to launch the largest motor without excessive voltage dip.

Most generator failures in industrial settings aren't from running overload. They happen the instant a large motor starts, when current can spike to 5 to 7 times its running value.

If the alternator can't supply that surge, voltage collapses, the excitation system loses control, and the engine stalls under the sudden mechanical load.

Cummins industrial diesel generator used to illustrate generator sizing for industrial loads
Image credit: Cummins Inc.
Advertisement
Advertisement

The 5 Steps to Calculate Generator Size

Work through these steps in order, since each one can change which number ultimately governs the final size.

1

List Every Load, Running and Starting

Sum nameplate kW for all loads that could run simultaneously, and separately note each motor's starting characteristics.

2

Apply a Diversity Factor

Not everything runs at once. Use roughly 0.6 to 0.85 for mixed industrial loads depending on how continuous the process is.

3

Calculate Starting kVA for the Largest Motor

Identify the biggest single starting event and calculate its kVA demand at the actual starting power factor.

4

Take the Larger of the Two Results

Compare running kVA against starting kVA. The generator must satisfy whichever number is bigger.

5

Apply Site Derating and Spare Capacity

Account for altitude, ambient temperature, and future load growth before finalizing the selection.

Running Load vs Starting Load

These represent two completely different demands on the same machine.

Running Load

Steady-state demand once everything is up and running. Usually the smaller number, but it's continuous.

Sustained, thermal limit
🔥

Starting Load

A brief but severe transient, often 5 to 7 times running current at a very low power factor during motor start.

Transient, alternator limit
Advertisement
Advertisement

Why Undersized Generators Stall

The failure sequence is mechanical, not just electrical, and it happens fast.

Motor starts: current surges, generator terminal voltage sags
Excitation system tries to recover voltage, drawing more field current
If the alternator can't keep up, voltage collapses and the engine stalls under load

Voltage dip during motor starting should generally stay below 15 to 20 percent. Push past that and other running equipment, drives, contactors, control relays, can trip or reset well before the engine itself gives up.

Why voltage dip is a system-wide concern, not just a generator spec

Sizing Formulas and a Worked Example

Both running and starting requirements reduce to a kVA figure that the generator must be able to supply.

Running kVA and Motor Starting kVA
Running kVA = Diversified kW / PF  |  Starting kVA = Motor kW x SCR x 1.2
Where SCR = starting current ratio (typically 5 to 7 for DOL start)
PF = power factor (use about 0.8 for mixed industrial loads)

Example: 350 kW MCC, 0.6 diversity, largest motor 100 kW, SCR = 6
Running load = 350 x 0.6 = 210 kW -> 210 / 0.8 = 262.5 kVA
Starting kVA = 100 x 6 x 1.2 = 720 kVA
Governing requirement: 720 kVA (starting) -> select 875 kVA with margin

Starting Multiplier by Motor Starting Method

How a motor starts changes the generator sizing dramatically.

Starting MethodTypical MultiplierStarting Power Factor
Direct-On-Line (DOL)Approximately 2x motor kW minimum, often more0.15 to 0.30 lagging
Soft StarterApproximately 1.2 to 1.3x motor kWImproved over DOL
Variable Frequency Drive (VFD)Approximately 1.1 to 1.15x motor kWBest of the three methods

Site Derating: Altitude and Temperature

Unlike a transformer, a generator's engine derates because thinner air reduces combustion oxygen, not because of cooling or insulation.

ConditionTypical Derating
Naturally aspirated diesel, per 1000 ft above sea levelApproximately 3 to 4% output loss
Turbocharged diesel, per 1000 ft above sea levelApproximately 1 to 2% output loss
High ambient temperatureManufacturer-specific curve, consult datasheet

Where Correct Generator Sizing Matters Most

🏭

Motor Control Centers

Multiple motors with a dominant largest-motor starting event.

🏥

Hospitals

NEC Article 700 emergency systems with life safety loads.

🖥

Data Centers

Low power factor, harmonic-rich UPS and cooling loads.

Oil and Gas Sites

Remote, often high altitude installations needing derating.

💧

Water and Wastewater

Large pump motors with harsh DOL starting duty cycles.

Manufacturing Plants

Compressors and conveyor motors starting on a staggered schedule.

Do's and Don'ts of Generator Sizing

✓ Do

  • Size for the larger of running kVA and starting kVA, never running alone
  • Use the actual starting method's multiplier, not a generic rule of thumb
  • Apply altitude and temperature derating for the actual installation site
  • Sequence large motor starts where possible to reduce peak starting demand

✗ Don't

  • Assume a generator's kW rating alone covers a low power factor load
  • Ignore voltage dip limits when multiple large motors start together
  • Ship a generic sizing result without verifying against manufacturer software
  • Forget that DOL starting can demand 2 to 3 times the motor's running kW
Advertisement
Advertisement

Live Generator Sizing Calculator

Enter running load, power factor, diversity, and the largest motor's starting details to estimate the required generator kVA.

🧮 Industrial Generator Sizing Calculator
-
Running kVA
-
Starting kVA
-
Governing kVA

Load Dump: The Opposite Failure Mode

Undersizing isn't the only risk. Sudden loss of a large load, a main breaker tripping open, creates the reverse problem entirely.

In island mode, if 100 percent of the load disappears instantly, the engine can overspeed since there's no longer any mechanical resistance from the alternator.

Manufacturers specify load dump capability, typically the ability to shed 100 percent of load for 10 to 15 seconds without tripping. This needs the same careful review as motor starting during the design phase, not an afterthought.

Advertisement
Advertisement

Reference Materials on Generator Sizing

PDF
Basic Sizing for Mobile Generators
Generac white paper: kVA, power factor, and motor starting fundamentals
PDF
A Brief Guide to Interpreting a SpecSizer GenSet Sizing
Caterpillar dealer technical guide: running kW, starting kVA, and alternator sizing

FAQs on How to Calculate Generator Size for an Industrial Load

What's the basic rule for sizing a generator with motors?
Size the generator for the larger of two numbers: the total running kVA at the site's power factor, or the starting kVA needed for the largest motor, since a direct-on-line start can demand 2 to 3 times the motor's running kW.
Why are generators rated in kVA rather than kW?
Generator sets are typically rated in kVA at a 0.8 lagging power factor, since real kW output depends on the connected load's power factor, and using kVA ensures the alternator's thermal and current capacity is adequate regardless of load characteristics.
How much voltage dip is acceptable during motor starting?
A common guideline keeps transient voltage dip below 15 to 20 percent during the largest motor start, since exceeding that can trip variable frequency drives, reset controls, or cause visible lighting flicker on other circuits.
Does a soft starter or VFD reduce the required generator size?
Yes significantly, since soft starters typically need only about 1.2 to 1.3 times the motor's kW to start it, and VFDs need about 1.1 to 1.15 times, compared to 2 times or more for direct-on-line starting.
Why does altitude derate a generator differently than a transformer?
A generator's diesel engine loses output at altitude because thinner air provides less oxygen for combustion, roughly 3 to 4 percent per 1000 feet for naturally aspirated engines, while a transformer derates due to reduced cooling and dielectric strength instead.
Should I trust a simplified sizing calculation for a final generator purchase?
Use it only as a preliminary screening figure, then verify with the manufacturer's own sizing software, such as Cummins PowerSuite or Caterpillar SpecSizer, which accounts for site-specific derating, transient response, and actual product ratings.

External References

What we learn today

  • How to calculate generator size for an industrial load means comparing running kVA against motor starting kVA and sizing for whichever is larger.
  • Direct-on-line motor starting can demand 2 to 3 times the motor's running kW, while soft starters and VFDs need far less.
  • Undersized generators stall because voltage collapse during motor starting overwhelms the excitation system, not from steady overload.
  • Voltage dip during the largest motor start should generally stay below 15 to 20 percent to protect other running equipment.
  • Generators derate with altitude because thinner air reduces combustion oxygen, roughly 3 to 4 percent per 1000 feet for naturally aspirated diesel engines.
"I hope you like above blog. There is no cost associated in sharing the article in your social media. Thanks for reading!! Happy Learning!!"

Leave a Reply

Your email address will not be published. Required fields are marked *